The simple and quick way to get resources leveled is to set Finish-to Start link for tasks using the same resource. Res1 is over-allocated by doing two tasks at the same time or in terms of MS Project Res1 has 100% units allocated...

This is about how to simplify planning. Each company has a project history with schedules already done. So, we can use it. Save frequently used schedule parts as .mpt templates and put in 'Task-Set templates' folder in Construction Project root directory. Then...

Export Export current project to the following formats used worldwide to exchange project's data. .MPX format. Used frequently to export MS Project data into other system.   .XML or so called MSPDI format. (MS Project can save project as .xml and that is initially MSPDI format ) Import Imports project data...